|
Waste (present): 21,000 m3 L/ILW; 1,800 MT spent fuel; Annual production L/ILW 1,200 m3 and 160 MT spent fuel; L/ILW disposed at El Cabril surface disposal; spent fuel stored at reactor site. Waste (future, cumulative): 200,000 m3 L/ILW; 10,500 m3 HLW (6,750 MT spent fuel and 200 m3 VHLW); L/ILW until 2015 capacity at El Cabril; spent fuel at reactor site or possibly at Trillo interim storage facility; disposal strategy HLW yet unknown. Waste authorities: Empresa Nacional de Residuos Radioactivos SA (ENRESA). Retrievability: surveillance period at El Cabril of 300 years; strategy for HLW unknown. Dialogues (among others): Senate Commission for Industry set up inquiry commission in 1996, report not adopted in Senate, broad support was lacking. Key issues: politics appears to be imposing difficulties in dealing with the nuclear waste problem; interim storage at Trillo might postpone further decisions; with this, an acceptable solution is not near. |
Introduction
After a presentation on the
waste policy of Spain at a conference[1] and
upon receiving information on an inquiry by the Spanish Senate, CORA requested
us to include Spain to our list of countries to be studied. We agreed with
the request but found some difficulties in describing the country. These
difficulties deal in one part with a shortage of English material about
Spain, and also the choice not to visit that country to have extensive
interviews because of time and fund constraints. Therefore, this chapter
will be shorter than the others. This is also because of the fact that
the inquiry outcome was unsuccessful, its report was rejected by the Senate
and the commission was disbanded.
For this chapter, the information
was found in a number of documents, mainly from the OECD/NEA, the waste
authority "Empresa Nacional de Residuos Radioactivos SA" (ENRESA), and
the WISE News Communique. Telephone conversations were made with representatives
from ENRESA. Unfortunately, no environmental organisation reacted to our
requests for information. Their view is presented through the use of the
WISE News Communique as a source. A draft version of the chapter was commented
upon by Elena Vico and collegues at ENRESA.
Spain's first nuclear reactor
was opened in 1968. Aside from a now gas-graphite reactor which has been
shut down, all the nine reactors are of the light-water design. Nuclear
energy has a 34% share in total electricity production and a generating
capacity of 7.1 GWe. Based on its National Energy Plan 1991-2000, no new
nuclear capacity is foreseen[2].
2. PRODUCERS OF RADIOACTIVE WASTE
Main producers of nuclear waste
are the nuclear power plants that are responsible for about 95% of the
radioactive waste that would be produced in the coming decades. Other producers
are, for instance, medical and industrial isotope users[3].
3. CATEGORIES OF RADIOACTIVE WASTE
Spain knows two categories of
radioactive waste. The first one is low- and intermediate-level waste that
has a low specific activity, short-lived beta and gamma emitters and a
low concentration of long-lived alpha isotopes. The category high-level
waste has a high specific activity, a higher concentration of long-lived
isotopes or is heat generating[4].
4. AMOUNTS OF RADIOACTIVE WASTE
4.1 Present amounts
Till the end of 1995, 21,000
m3 low- and medium-level waste and about 1,800 MT(U) of spent
fuel were stored. Annual production of low/medium-level waste was 1,200
m3 and 160 tU of spent fuel. Spent fuel of the closed Vandellós-1
was sent to the reprocessing plant La Hague in France. In 1983, however,
the government decided to stop reprocessing. Vitrified high-level waste
is to be returned to Spain in the future[5].
4.2 Future amounts
Based on a 40-year lifetime
of nuclear reactors, a total of 200,000 m3 of low- and intermediate-level
waste has to be stored in the future. Main part of this are wastes that
arise from dismantling (64%). Others are, for instance, operating wastes
from reactors (23%) or other producers (5%). A total of 10,500 m3
of high-level wastes have to be stored, being 6,750 MT of spent fuel and
200 m3 vitrified reprocessing waste[6].
Low- and intermediate-level waste
is disposed of at the El Cabril surface disposal facility. This facility,
located in the province of Córdoba at the location of an abandoned
uranium mine, was opened in 1992 and can store waste till about 2015. The
waste packages are stored inside big concrete containers of about 2 x 2
x 2 meters. The blocks are covered with protective structures and later
covered with earth. A surveillance period for 300 years is foreseen[7].
Spent fuel is stored at the
reactor sites. As there is no final storage yet, three options are open
for interim storage. Reracking inside the reactor cooling pools will increase
storage capacity. Other possibilities are the construction of on-site storage
casks or a centralised interim facility[8]. According
to ENRESA, reracking has been completed at all reactors and the storage
casks are licensed to be used as further expansion capacity increases[9].
The construction of a centralized interim facility would not be really
necessary till the year 2010. So, research is being conducted on this option,
but no specific plans of a site have been made, says ENRESA[10].
However, environmental groups
protested against a 1999 government decision to give the green light for
a waste storage facility at the Trillo nuclear power station, which they
feared would become the de facto centralized interim storage as mentioned.
According to Ecologistas en Accion, the facility, which is said to be necessary
as spent fuel pools in Trillo would be filled in 2003, would have a storage
capacity that could store twice as much as the Trillo spent fuel produced
and would be easily expandable. As the Trillo power station is owned by
almost all the electric utilities, they fear the companies would "solve"
the waste problem with this facility. The government decision overruled
two earlier refusals by the city council and the Superior Court of Justice,
because of "urgency or exceptional public interest"[11].
ENRESA is the organisation responsible
for waste management. It is a state-owned company that was set up in 1984
to deal with all the aspects of waste management.
The Ministry of Industry and
Energy is responsible for legislation and licensing, together with the
Nuclear Safety Council (CSN). CSN was set up in 1980 and deals with nuclear
safety and radiological protection and reports directly to the Senate[12].
Initially, ENRESA searched for
favourable rock formations of salt, clay and crystalline. The research
program started in 1987 and at that time a repository was expected to be
realised by 2020. By end-1990, some 25,000 km2 of possible regions
were found. Finally, some 30 areas were identified for further research[13].
Although ENRESA had identified
the favourable areas for further underground research, work was halted
in 1996 due to public opposition. In 1995, it became known among environmental
groups that ENRESA had plans for the construction of underground disposal
sites and a list of possible locations was released. They accused ENRESA
of not having informed the public and of having inspected possible sites.
Big demonstrations were organised, the first one in Belaleazar with 10,000
persons in 1996. The year after, some 15,000 demonstrated at Villanueva.
It even grew to 20,000 in 1998 at Torrecampo[14]. And
although decisions about underground disposal and test drillings were not
to be taken before 2010, the protests have continued. Also in early 1999
a demonstration with thousands of participants was organised[15].
At the end of 1996, the Senate
Commission for Industry established an inquiry commission to develop a
new waste policy. It had to study the difficulties in finding a site for
waste disposal and should include socio-political and public acceptance
aspects. The commission’s work was expected to result in guidelines for
the government to develop a legal framework for siting. The commission
also received contributions from groups and institutions. The commission
also visited other countries for comparison.
In the process, the government
decided in early 1998 not to make decisions about final disposal before
the year 2010. By that time the Senate should have evaluated the research
being conducted. It was also decided to conduct site drillings only after
2010 and that a voluntary process had to be "expected" before these could
take place. More research should be done on partitioning and transmutation.
For ENRESA, the government decision
meant that no test drilling work could be done. Studies do continue with
the use of existing geological data[16].
By the end of 1998, the inquiry
commission had come to conclusions and made recommendations to the government
on how to proceed with the waste policy. But its report was not adopted
at the April 1999 Senate plenary meeting and the commission was disbanded.
Although it is not really clear what the exact reasons were for the rejection
of the darft report, it appeared to be for political reasons. Where the
commission had reached consensus about certain issues, in the Senate the
report did not get the broad support that was wanted by the government.
The government wanted the broad
support of the main political parties to accept it, but the Parti Popular
and the Socialist Party voted against it. "It did not reflect their opinions,"
said an ENRESA spokeswomen, "and political parties do not want to talk
about high-level waste"[17]. It remains unclear how
the Spanish government would now proceed. It was expected that after an
adoption of the inquiry report, new laws would be developed to give a legal
framework for Spain’s policy. New laws would be necessary for future siting
activities[18].
ENRESA has been preparing a
new General Radioactive Waste Plan. Although ENRESA has the obligation
to submit yearly a proposal for a plan, the government has no obligation
to approve it every year[19]. In July 1999, the cabinet
agreed to approve the fifth plan. In this plan, the postponement until
2010 of decisions on deep disposal was included. Earlier plans fixed the
decision for constructing an underground storage facility in 2000. According
to Ecologistas en Accion, this delay has to do with upcoming general elections,
public opposition and delays in international research and programs[20].
As in other countries, plans
for an underground storage or research program have faced public opposition
in Spain. Siting work by ENRESA stopped in 1996 after this opposition.
Although research continues with already known geological data, no site
drillings are to take place before 2010. By that year the Senate has to
decide on a final disposal strategy.
Government licensed the building
of a spent fuel storage facility at the Trillo nuclear power plant. Environmental
groups fear that this storage might become a national storage facility.
An inquiry commission was set
up to give guidelines in the development of a new policy that could overcome
public opposition. But after having written a draft report, the final outcome
was unsuccessful. The report was not adopted in the Senate due to what
appears to be political reasons.
1. As it remains unclear what
the exact reasons were to reject the report, it looks more that the waste
issue is so controversial that political parties have difficulties in dealing
with it.
2. The realisation of an interim
storage at Trillo, firstly meant for the station itself but with a possibility
of expansion, can result in decisions being easily postponed in the future.
3. The political hesitations
and the practice of postponing has not brought and will not bring an acceptable
solution any closer.