New-generation Finnish nuclear reactor hit by fourth delay The Guardian 18 October 2008 01-11-2008 SDS CONSTRUCTION NUCLEAR POWER PLANT EPR FINLAND COSTS NUCLEAR ENERGY
Nuclear power costs: High and higher Makijani, Arjun 01-01-2008 SDA CONSTRUCTION NUCLEAR POWER PLANT ELECTRICITY PRICE ENERGY EPR FINANCING FINLAND COSTS NUCLEAR ENERGY COST COMPARISON RESEARCH INSTITUTEN UNITED STATES OF AMERICA
French firm to build unproven reactors in China New York Times, Nov. 27, 2007 01-12-2007 NUKW AREVA GROUP CONSTRUCTION NUCLEAR POWER PLANT CHINA EPR FRANCE CONTRACTS COSTS NUCLEAR ENERGY POLICY
Protest auf EPR-Baukran in Olkiluoto Totz, Sigrid 01-07-2007 AAA ACTIONS CONSTRUCTION NUCLEAR POWER PLANT EPR FINLAND GREENPEACE COSTS NUCLEAR ENERGY OLKILUOTO, FINLAND
EPR: Un réacteur qui prend du retard 01-02-2007 SIL EPR FRANCE COSTS NUCLEAR ENERGY COST COMPARISON SUPERPHENIX
PBMR - Es geht voran! 01-01-2007 THTR WASTE GENERAL CONSTRUCTION NUCLEAR POWER PLANT GERMANY ENSA EPR HAMM, THTR, DUITSL. COSTS NUCLEAR ENERGY NUKEM PBMR PELINDABA, Z-AFRIKA PLUTONIUM SOUTH AFRICA
EPR: Finlande : problèmes divers 01-01-2007 SIL AREVA GROUP EPR EU / EC GREENPEACE COSTS NUCLEAR ENERGY SUBSIDIES FOR NUCLEAR POWER TVO ENSURANCES
Areva: Olkiluoto-3 not "A bag of chips"  (650.5768) Wise Amsterdam 15-12-2006 NM AREVA GROUP CONSTRUCTION NUCLEAR POWER PLANT EPR FINANCING FINLAND FRAMATOME ANP FRANCE COSTS NUCLEAR ENERGY OLKILUOTO, FINLAND TVO
L'EPR : un danger pour l'homme et pour l'environnement infonucleaire@altern.org 01-09-2006 GN ANTI-NUCLEAR MOVEMENT GERMANY EPR FLAMANVILLE EPR, FRANCE FRANCE COSTS NUCLEAR ENERGY LOBBY COMPANIES NUCLEAR LOBBY OPINION POLLS COOPERATION REACTOR SAFETY
Honeymoon mine to proceed Uranium One 29/8/06 01-09-2006 UICW HONEYMOON IN SITU LEACHING COSTS NUCLEAR ENERGY URANIUM MINING URANIUM RESOURCES & PRICE LICENSES
Gemeinsam gegen das europäische Atommüll-Endlager in Bure 01-07-2006 AAA ANTI-NUCLEAR MOVEMENT ACTIONS ANDRA BURE EPR FRANCE COSTS NUCLEAR ENERGY RESEARCH INSTITUTEN POLICY
Un courant alternatif pour le grand ouest: Quelles alternatives au réacteur EPR 01-06-2006 SORT DEMOCRACY ECONOMY – GENERAL ENERGY POLICY, GENERAL ENERGY POLICY, NUCLEAR EPR FRANCE COST - GENERAL COSTS NUCLEAR ENERGY COST COMPARISON EMPLOYMENT
France to construct new reactor EdF 4/5/06 12-05-2006 UICW CONSTRUCTION NUCLEAR POWER PLANT EDF ELECTRICITY PRICE ENEL EPR FLAMANVILLE EPR, FRANCE FRANCE COSTS NUCLEAR ENERGY
Bilan de Cherbourg Libération 15/04/2006; Reuters 15/04/2006; Le Monde 15/04/06 01-05-2006 STG ACTIONS CENSORSHIP EPR FRANCE NUCLEAR ENERGY COSTS NUCLEAR ENERGY RISK ANALYSE
Nuclear power - myth and reality: 9. Cheap nuclear power: If the state foots the  Rosenkranz, Gerd 21-04-2006 NM GLOBAL IMPORTANCE OF NUCLEAR POWER CONSTRUCTION NUCLEAR POWER PLANT ECONOMY – GENERAL ENERGY EPR FRAMATOME ANP COSTS NUCLEAR ENERGY COST COMPARISON LIFETIME EXTENSION OLKILUOTO, FINLAND POLICY SUBSIDIES FOR NUCLEAR POWER UNITED STATES OF AMERICA
Petite contribution au débat public EPR Robert Pouyfaucon 01-11-2005 GN DEMOCRACY EDF ELECTRICITY EPR FRANCE HIGH TENSION NETWORK COSTS NUCLEAR ENERGY COST COMPARISON LOCATION NEW NUCLEAR FACILITY OPINION GENERAL REACTOR SAFETY
Goed perspectief voor de EPR in Frankrijk 01-09-2005 NSK CONSTRUCTION NUCLEAR POWER PLANT EDF EPR FLAMANVILLE EPR, FRANCE FRANCE COSTS NUCLEAR ENERGY
Retard en vue pour l'EPR français 01-07-2005 SORT AREVA GROUP EPR EXPORT FRANCE COSTS NUCLEAR ENERGY LOBBY COMPANIES RESEARCH INSTITUTEN SIEMENS - KWU
Swedish reactor shuts down Nucleonics Week 2/6/05 01-07-2005 WNA BARSEBÄCK, SWEDEN CONSTRUCTION NUCLEAR POWER PLANT EPR COSTS NUCLEAR ENERGY CLOSURE TVO
EdF seeks investment in new reactor 18-03-2005 UICW CONSTRUCTION NUCLEAR POWER PLANT EDF ENEL EPR FLAMANVILLE EPR, FRANCE FRANCE IMPORTATION NUCLEAR ELECTRICITY ITALY COSTS NUCLEAR ENERGY TENDER
Pourquoi il faut sortir du nucléaire 01-01-2005 SORT EPR FRANCE COSTS NUCLEAR ENERGY PROLIFERATION RISK ANALYSE SAFETY GENERAL
Reclaiming the land: History of uranium mill tailings clean-up 01-09-2004 VFE DOE - USA COSTS NUCLEAR ENERGY CLEANUP SITES URANIUM MINING UNITED STATES OF AMERICA
Entscheidung für EPR 01-06-2004 AAA IMPORTANCE NUCLEAR IN TOTAL ENERGYPRODUCTION CONSTRUCTION NUCLEAR POWER PLANT ENERGY POLICY, NUCLEAR EPR COSTS NUCLEAR ENERGY GOVERNMENT
European Pressurised water Reactors - talks grind on 01-06-2004 WANA CONSTRUCTION NUCLEAR POWER PLANT EPR FINLAND FRAMATOME ANP CONTRACTS COSTS NUCLEAR ENERGY SIEMENS - KWU
Jeûne: Vivre sans nucléaire à partir du 21 juin 2004 à Paris Jeûne Vivre sans nucléaire 01-06-2004 SORT ANTI-NUCLEAR MOVEMENT ACTIONS EPR FRANCE COSTS NUCLEAR ENERGY COST COMPARISON RESEARCH INSTITUTEN OPINION POLLS
Nicolas Sarkozy, VRP du lobby nucléaire ! Stéphane Lhomme 01-06-2004 SORT GREENHOUSE EFFECT ENERGY POLICY, GENERAL EPR EU / EC FRANCE ILLEGAL OPERATION COSTS NUCLEAR ENERGY LOBBY COMPANIES NUCLEAR LOBBY GOVERNMENT THERMAL EFFECTS
Le nucléaire échappe à la rigueur budgétaire ! Greenpeace; Frédéric Marillier 01-06-2004 SORT EPR FRANCE GREENPEACE COSTS NUCLEAR ENERGY COST COMPARISON GOVERNMENT SUBSIDIES FOR NUCLEAR POWER
Wind gegen Atom Greenpeace 01-04-2004 AAA ACTIONS CONSTRUCTION NUCLEAR POWER PLANT EDF ENERGY EPR FRANCE GREENPEACE COSTS NUCLEAR ENERGY PENLY, FRANCE
EPR 01-04-2004 AAA GERMANY EPR FRANCE COSTS NUCLEAR ENERGY GOVERNMENT
Face à l'EPR, d'autres choix énergétiques sont possibles ! 01-04-2004 SIL ANTI-NUCLEAR MOVEMENT ACTIONS ENERGY POLICY, NUCLEAR EPR FOE GREENPEACE