A plan to construct 11 new nuclear power reactors by 2030 |
|
11-05-2005 |
WNAN |
AFVAL DROGE INTERIM BOUW VAN KERNCENTRALE ENERGIEBELEID KE KHMELNITSKI, SU OEKRAINE REGERING |
Approval for the first concrete to be poured at the site of the Kudankulam... |
Nucleonics Week, 28 March, p6; NucNet News, 125/02, 2 April |
03-04-2002 |
WNAN |
AERB, INDIA BOUW VAN KERNCENTRALE INDIA KAIGA, INDIA KOSTEN KERNENERGIE PWR RAJASTHAN RAPS,INDIA |
Construction of the Cigar Lake uranium mine will be delayed |
Cameco, 23 October |
18-10-2006 |
WNAN |
BOUW VAN KERNCENTRALE CANADA CIGAR LAKE ONGELUKKEN REST OPSTARTEN |
Construction of three nuclear power reactors would be accelerated |
|
17-03-2004 |
WNAN |
BOUW VAN KERNCENTRALE INDIA KAIGA, INDIA KUDANKULAM, INDIA NPCIL, INDIA RAJASTHAN RAPS,INDIA TARAPUR, INDIA TECHNISCH ALGEMEEN |
India starts construction of two more reactors |
Power in Asia 17/10/02 |
01-12-2002 |
WNAN |
BOUW VAN KERNCENTRALE INDIA KOSTEN KERNENERGIE RAJASTHAN RAPS,INDIA |
India: The first concrete was poured at the site of the Rajasthan-5 and -6... |
NucNet News, 357/02,13 November; see also NB 02.39-9 |
19-11-2002 |
WNAN |
BOUW VAN KERNCENTRALE CANDU INDIA RAJASTHAN RAPS,INDIA |
Nuclear Power Corp of India Ltd (NPCIL) reported... |
Nucleonics Week, 12 September, p7; see also NB 01.50-5 |
24-08-2002 |
WNAN |
BOUW VAN KERNCENTRALE INDIA KAIGA, INDIA KOSTEN KERNENERGIE RAJASTHAN RAPS,INDIA TARAPUR, INDIA |
Work has started on the construction of Kaiga-3 and -4 |
|
10-04-2002 |
WNAN |
AERB, INDIA BOUW VAN KERNCENTRALE INDIA KAIGA, INDIA PWR RAJASTHAN RAPS,INDIA VEILIGHEID REACTOR |