date INES title location
1990-07-01INES 2IMPACT ON SAFETY DUE TO VIOLATION OF OPERATIONAL LIMITS AND CONDITIONS (IMPURITY DUE TO AIR INGRESS)FranceCREYS-MALVILLE
1990-05-28INES 1FEEDWATER TUBE RUPTURE DUE TO EROSION CORROSIONFinlandLOVIISA-1
1990-04-24INES 0STICKING OF SHIELD PLUG IN THE FUEL CHANNELPakistanKANUPP
1990-02-23INES 2REACTOR COOLANT LEAK ON THE WATER CLEANING SYSTEM WHILE CONNECTED TO THE PRIMARY CIRCUITGermanyGreifswald
1990-01-23INES 2REACTOR COOLANT LEAK DURING ON POWER REFUELLING DUE TO FUELLLING MACHINE DROPCanadaBRUCE-4
1990-01-05INES 0AUTOMATIC PLANT SHUTDOWN DUE TO AN EARTHQUAKESloveniaKRSKO
1990-01-01INES 1FUEL BUNDLE LATTICE SPACING FAILURESFinlandLOVIISA-1
1989-06-26INES 0FAILURE OF THE MAIN FEEDWATER PUMP DUE TO ABSENCE OF REQUALIFICATION TEST AFTER MAINTENANCEJapanTSURUGA-2
1988-06-30INES 1DEGRADATION OF NATURAL CIRCULATIONHungaryPAKS-4
1987-11-20INES 2CRITICALITY SHUT DOWN MARGIN MEASUREMENT STARTED WITHOUT HYDRAULIC SCRAM SYSTEM BEING OPERABLESwedenOSKARSHAMN-3
1974-08-20INES 2EXCESSIVE DEPRESSURIZATION OF THE PRIMARY CIRCUIT DUE TO A PRESSURIZER SAFETY VALVE THAT FAILED TO CLOSESwitzerlandBEZNAU-1