From the publication:

REPORT BY THE
Comptroller General
OF THE UNITED STATES

Nuclear Power Costs And Subsidies

On October 23, 1978, Senator John Melcher asked GAO to identify, to the extent 
possible, the "full" cost of nuclear power. Such a cost mainly includes not only 
industry's costs, but also those borne by the Federal Government to promote or 
regulate the nuclear power industry.

GAO found that the average commercial cost of electricity generated, by nuclear 
power-plants in the United States during 1978 was reported to be about 1.5 cents 
per kilowatt-hour, about the same as it was in 1977.

Major Federal nuclear-related costs and subsidies for research and development, 
uranium enrichment, uranium exploration, and regulation totaled about $1.7 billion 
during fiscal year 1978, an increase of about $274 million from fiscal year 1977. 
These costs, based on assumptions described in the report, were equal to 0.62 cents 
per kilowatt-hour during fiscal year 1978, and 0.57 cents during fiscal year 1977. 
Other Federal contributions to the nuclear industry described in the report were 
not quantifiable.