Front

From the publication:

                           EUROPEAN
                           COMMISSION




                                                   Brussels, 4.10.2012
                                                   SWD(2012) 287 final




                    COMMISSION STAFF WORKING DOCUMENT

       Technical summary on the implementation of comprehensive risk and safety
              assessments of nuclear power plants in the European Union

                               Accompanying the document

     COMMUNICATION FROM THE COMMISSION TO THE COUNCIL AND THE
                      EUROPEAN PARLIAMENT

     on the comprehensive risk and safety assessments ("stress tests") of nuclear power
                   plants in the European Union and related activities

                                  {COM(2012) 571 final}




EN                                                                                        EN
                                         TABLE OF CONTENTS

1.      THE EU NUCLEAR STRESS TESTS: APPROACH AND METHODOLOGY ........................ 4
1.1.    The peer review process............................................................................................. 4
2.      KEY RECOMMENDATIONS FROM THE SAFETY ASSESSMENTS ..................................... 5
2.1.    Specific recommendations on external hazards ...................................................... 5
2.2.    Specific recommendations on loss of safety functions ............................................ 6
2.3.    Specific recommendations on severe accident management.................................. 6
2.4.    Aircraft crashes .......................................................................................................... 6
3.      KEY RECOMMENDATIONS FROM THE SECURITY ASSESSMENTS ................................. 7
4.      MORE DETAILED TRANSVERSAL AND GENERIC RESULTS OF THE SAFETY
        ASSESSMENTS ............................................................................................