TMIA: THREE MILE ISLAND ALERT, INC.

CHRONOLOGY OF PROBLEMS AT PEACH BOTTOM

The Nuclear Regulatory Commission (NRC) and the Institute for Nuclear Power 
Operations (INPO) have clearly demonstrated that Philadelphia Electric's (PECO) 
performance has historically been lackadaisical and sub-par. In order to put 
Peach Bottom's operating history into perspective, it is necessary to review 
PECO's plant legacy.

- March, 1983 - A spill of 25,000 gallons of radioactive water was reported
at the plant.

- June 1983 - PECO was fined $40,000 by the NRC for a valve violation.

-July 1983 - Philadelphia Electric: identified cracks in their cooling pipes.

- 1983 -1987 - PE was issued a number of violation notices that cost the utility
$485,000 in civil penalties. All the violations involved failure of personnel 
to follow procedures.

Examples of violations include: workers entering high radiation areas without 
required radiation protection; improperly controlling access keys to the plant's 
high radiation areas; discrepancies in workers' radiation work permits; improper 
packing of low level radioactive wastes; leaving air lines open while the reactor 
was producing power between August 12 and September 10, 1982. With these lines 
open the containment could not be sealed against radiation escape in the event of an 
accident; all owing excessive leakage from the containment building; improperly 
setting instrument valves which made the plant incapable of providing back-up 
signals to automatically shut the reactor down in the event of an accident 
(Lancaster Independent Press, April, 1988).