INES-event
INES 0

DAMAGE TO RCP MAIN THRUST BEARING WHILE PREPARING PRIMARY FOR HYDROTEST

While performing primary circuit warmup after preventive maintenance prior to leak tightness hydrotest at 10:48 damage to RCP-3 main thrust bearing occurred. The affected pump was tripped. The event had no consequences.
No breach of limiting conditions for operation occurred.
BASIS FOR RATING:
DIFFICULTIES IN RATING:

Location: KOLA-3
Event date: Sat, 07-12-1991