02-01-1993INES 1SMALL STEAM LEAK FROM THE MAIN FLANGE OF THE PRIMARY COOLANT PUMP NO. 4KOZLODUY-2, Bulgaria
01-11-1992INES 1INDICATIONS IN AUSTENITIC PIPING DISCOVERED DURING NON-DESTRUCTIVE TESTINGBRUNSBUETTEL, Germany
24-02-1993INES 1CRACKS IN PIPEBENDS (ELBOWS) IN THE RESIDUAL HEAT REMOVAL SYSTEMOSKARSHAMN-1, Sweden
12-02-1993INES 1PLUTONIUM RECOVERY PLANT, B204BNFL, Sellafield, United Kingdom
27-05-1993INES 1UNIT SCRAM DUE TO INADVERTENT ACTUATION OF PRESSURIZER PILOT RELIEF VALVEKOLA-3, Russian Federation
02-02-1993INES 1UNIT SCRAM CAUSED BY GRID DISTURBANCES DUE TO TORNADOKOLA-3, Russian Federation
02-02-1993INES 1UNIT SCRAM CAUSED BY GRID DISTURBANCES DUE TO TORNADOKOLA-4, Russian Federation
07-10-1993INES 1RADIOACTIVE CONTAMINATION OF THE UNIT ROOMS DUE TO REACTOR COOLANT LEAK IN THE AUXILIARY SYSTEMBELOYARSKY-3(BN-600), Russian Federation
26-11-1993INES 1HUMAN ERROR INITIATED SAFETY INJECTION/REACTOR TRIPKRSKO, Slovenia
12-10-1993INES 1IMPENETRABILITY TEST OF CONTAINMENT NOT APPROVEDBARSEBECK-2, Sweden
18-01-1994INES 1CRACK IN CONTROL ROD HOUSINGJOSE CABRERA-1 (ZORITA), Spain
07-02-1994INES 1FAILURE OF THE FOAM FIRE-EXTINGUISHING SPRINKLER SYSTEM TO OPERATE FOR 16 HOURS DUE TO FROZEN PIPESIGNALINA-1, Lithuania
16-03-1994INES 1REACTOR SCRAM CAUSED BY THE CABLE FIRE UNDER THE TURBINE HALL PREMISESKHMELNITSKI-1, Ukraine
21-12-1993INES 1TURBINE TRIP DUE TO PRESSURE DROP IN STEAM GENERATOR MAIN COLLECTORBOHUNICE-2, Slovakia
24-02-1994INES 1DETERIORATION OF THE PRIMARY CIRCUIT INTEGRITYIGNALINA-2, Lithuania
09-12-1993INES 1EXCEEDING OF CL-CONCENTRATION IN PRIMARY CIRCUIT WATERBOHUNICE-2, Slovakia
22-04-1993INES 1INTERVENTION OF AUTOMATIC POWER CONTROL (APC) DUE TO SPURIOUS SIGNALBOHUNICE-2, Slovakia
23-02-1993INES 1FALL DOWN OF CONNECTOR FRAGMENTS INTO THE REACTOR VESSELBOHUNICE-2, Slovakia
18-10-1993INES 1VIOLATION OF CHEMICAL REGIME OF STEAM GENERATOR FEED WATER (SGFW)BOHUNICE-3, Slovakia
03-06-1993INES 1DIESEL GENERATOR START FAILUREBOHUNICE-3, Slovakia
18-04-1994INES 1SCRAM DUE TO THE LEVEL DROP IN TANKS OF EMERGENCY REACTOR COOLING SYSTEMCHERNOBYL-3, Ukraine
18-04-1994INES 1INCORRECT SAFEGUARD REPORTINGRINGHALS-2, Sweden
15-05-1994INES 1DETERIORATION OF NATURAL CIRCULATION DURING REPAIR WORKS AT UNIT NO. 1KOZLODUY-1, Bulgaria
25-05-1994INES 1DEFECT OF MAIN GATE VALVE STUDSSOUTH UKRAINE-1, Ukraine
18-05-1994INES 1RUPTURE OF PRESTRESSED CABLE WIRES CONTAINMENTS DOME PARTSOUTH UKRAINE-1, Ukraine
11-07-1994INES 1MALFUNCTION IN THE SYSTEM OF NEUTRON CONTROL OF REACTOR POWER FOLLOWING THE REPLACEMENT OF A CONTROL ROD SWITCHIGNALINA-2, Lithuania
11-08-1994INES 1OVERFLOW OF A SOLUTION IN THE MAPU WORKSHOP (MEDIUM ACTIVITY PLUTONIM WORKSHOP) AT THE UP2-400 PLANTLA HAGUE, France
31-08-1994INES 1LEAKING ISOLATION VALVES IN THE EMERGENCY CORE COOLING SYSTEMBARSEBECK-2, Sweden
31-08-1994INES 1DAMAGE TO A SPENT FUEL ASSEMBLY DURING PREPARATORY OPERATIONS FOR REPROCESSINGMAYAK, RT-1, Russian Federation
17-10-1994INES 1THROUGH WALL CRACK OF THE UPPER PART OF THE FUEL CHANEL TRACT NO. 41-13CHERNOBYL-3, Ukraine