Hinkley Point C could be delayed to 2031 and cost up to £35bn, says EDF

[The Guardian]: "As nuclear plant is hit by further delay, real cost will be far higher after inflation is included, as project uses 2015 prices.
The owner of Hinkley Point C has blamed inflation, Covid and Brexit as it announced the nuclear power plant project could be delayed by a further four years, and cost £2.3bn more.
The plant in Somerset, which has been under construction since 2016, is now expected to be finished by 2031 and cost up to £35bn, France’s EDF said. However, the cost will be far higher once inflation is taken into account, because EDF is using 2015 prices.
The latest in a series of setbacks represents a huge delay to the project’s initial timescale. In 2007, the then EDF chief executive Vincent de Rivaz said that by Christmas in 2017, turkeys would be cooked using electricity generated from atomic power at Hinkley. When the project was finally given the green light in 2016, its cost was estimated at £18bn."

This Button was posted in and tagged with , on at 22:27 by .

Eén reactie op “Hinkley Point C could be delayed to 2031 and cost up to £35bn, says EDF

  1. Henk Boon, gelukzoeker

    Bouw Hickley kerncentrale duurt weer vier jaar langer, nu tot 2031. Kosten gestegen naar 35 miljard pond (prijspeil 2015!!!).Vergunning verleend in 2012, dus de totale bouwduur wordt 20 jaar. Als we dus in NL in 2025 een vergunning geven en het gaat even snel, dan staat-ie er in 2045 (kosten daargelaten). Zou dat nog zinvol zijn voor de energietransitie?#kerncentrale #kernenergie #energietransitie

About Stichting Laka

Het documentatie- en onderzoekscentrum kernenergie - Ketelhuisplein 43, Amsterdam - tel: 020-6168294 - mail: info@laka.org - Bsky: @laka.org - FB: facebook.com/stg.laka - Linkedin: company:stichting-laka - Mastodon: @laka@www.laka.org

Do you have a remark or did you spot an inconsistency? Let us know!

Related posts:

 

  • 10 February 2026: Authorized Noise: Normalising Risks

    Behnam Raeesian is an internationally recognized visual artist and poster designer from Iran, known for bold political and cultural works. Through exhibitions, workshops, jury roles, and collaborations with cultural institutions worldwide, he has built a strong voice in contemporary political graphic design. His projects confront complex issues such as nuclear risk and technological impact, transforming […]


  • 14 July 2025: The Nuclear Mirage: Why SMRs Won’t Save Nuclear Power

    Everywhere you look, the nuclear industry’s hype machine is in overdrive. Goldman Sachs, Microsoft, and the UK government all tout small modular reactors as the silver bullet for climate change and energy security. Tech billionaires are hiring nuclear veterans. Wall Street is whispering about “round-the-clock power” for artificial intelligence data centers. For those old enough […]


  • 25 March 2025: War games: aanval op Zuid-Korea’s nucleaire faciliteiten als ‘smoke-screen’ voor invasie Taiwan

    Kernenergie en veiligheid: A wargame sought to test if a major radiological release that would prompt the evacuation of millions of civilians in South Korea could distract key US allies from assisting and rebuffing an all-out military invasion of Taiwan. The short answer was yes. The game originally presumed that China, wanting to keep the […]


  • 22 November 2024: Problemen met nieuwe kerncentrale Olkiluoto in Scandinavië

    Big batteries and EVs to the rescue again as faults with new nuclear plant cause chaos on Nordic grids The Finnish nuclear power plant Olkiluoto was finally connected to the grid last year, at an estimated cost of €11 billion compared to the original budget of €3 billion. That cost blowout forced its developer, the […]


  • 6 May 2024: UK: Estimated cost of undersea nuclear graveyard now £66bn

    A vast subsea nuclear graveyard planned to hold Britain’s burgeoning piles of radioactive waste is set to become the biggest, longest-lasting and most expensive infrastructure project ever undertaken in the UK. The project [UK's nuclear waste dump] is now predicted to take more than 150yrs to complete with lifetime costs of £66bn in today’s money...The […]


  • 20 April 2024: Chemelot: SMR at Limburg chemical cluster undesirable

    Last year, the Dutch Province of Limburg started an alliance in which, besides the local government, research institutes, small nuclear reactor (SMR) developers, utilities, industrial customers and funders cooperated. With this "Limburg SMR alliance" Limburg  tried to lead the way towards an SMR in Limburg. The preferred site for a first SMR would be Chemelot, […]



Eén reactie op “Hinkley Point C could be delayed to 2031 and cost up to £35bn, says EDF

  1. Henk Boon, gelukzoeker

    Bouw Hickley kerncentrale duurt weer vier jaar langer, nu tot 2031. Kosten gestegen naar 35 miljard pond (prijspeil 2015!!!).Vergunning verleend in 2012, dus de totale bouwduur wordt 20 jaar. Als we dus in NL in 2025 een vergunning geven en het gaat even snel, dan staat-ie er in 2045 (kosten daargelaten). Zou dat nog zinvol zijn voor de energietransitie?#kerncentrale #kernenergie #energietransitie