| date | INES | title | location |
| 14-07-1994 | INES 0 | AUTOMATIC SHUT DOWN OF THE REACTOR AFTER GENERATOR PROTECTION ACTIVATION | KRSKO, Slovenia |
| 11-07-1994 | INES 1 | MALFUNCTION IN THE SYSTEM OF NEUTRON CONTROL OF REACTOR POWER FOLLOWING THE REPLACEMENT OF A CONTROL ROD SWITCH | IGNALINA-2, Lithuania |
| 08-07-1994 | INES 0 | AUTOMATIC REACTOR SHUTDOWN CAUSED BY SPURIOUS CLOSING OF THE GATE VALVE AT THE PIPELINE FEEDING THE MAIN CONDENSATE HEATER WITH HEATING STEAM | IGNALINA-2, Lithuania |
| 09-07-1994 | INES 0 | RELEASE OF IODINE 131 FROM THE TURBINE SYSTEM AT RINGHALS 1 | RINGHALS-1, Sweden |
| 03-06-1994 | INES 2 | FAILURE TO COMPLY WITH TECHNICAL SPECIFICATIONS FOR OPERATION AT REACTOR 4 | TRICASTIN-4, France |
| 18-05-1994 | INES 1 | RUPTURE OF PRESTRESSED CABLE WIRES CONTAINMENTS DOME PART | SOUTH UKRAINE-1, Ukraine |
| 25-05-1994 | INES 1 | DEFECT OF MAIN GATE VALVE STUDS | SOUTH UKRAINE-1, Ukraine |
| 15-05-1994 | INES 1 | DETERIORATION OF NATURAL CIRCULATION DURING REPAIR WORKS AT UNIT NO. 1 | KOZLODUY-1, Bulgaria |
| 18-04-1994 | INES 1 | INCORRECT SAFEGUARD REPORTING | RINGHALS-2, Sweden |
| 06-04-1994 | INES 2 | DEFECT OF THE REACTOR PROTECTION SYSTEM LEVEL CONTROLLER OF THE STEAM GENERATOR | SOUTH UKRAINE-1, Ukraine |
| 18-04-1994 | INES 1 | SCRAM DUE TO THE LEVEL DROP IN TANKS OF EMERGENCY REACTOR COOLING SYSTEM | CHERNOBYL-3, Ukraine |
| 03-06-1993 | INES 1 | DIESEL GENERATOR START FAILURE | BOHUNICE-3, Slovakia |
| 18-10-1993 | INES 1 | VIOLATION OF CHEMICAL REGIME OF STEAM GENERATOR FEED WATER (SGFW) | BOHUNICE-3, Slovakia |
| 23-02-1993 | INES 1 | FALL DOWN OF CONNECTOR FRAGMENTS INTO THE REACTOR VESSEL | BOHUNICE-2, Slovakia |
| 22-04-1993 | INES 1 | INTERVENTION OF AUTOMATIC POWER CONTROL (APC) DUE TO SPURIOUS SIGNAL | BOHUNICE-2, Slovakia |
| 09-12-1993 | INES 1 | EXCEEDING OF CL-CONCENTRATION IN PRIMARY CIRCUIT WATER | BOHUNICE-2, Slovakia |
| 24-02-1994 | INES 1 | DETERIORATION OF THE PRIMARY CIRCUIT INTEGRITY | IGNALINA-2, Lithuania |
| 31-03-1994 | INES 2 | ACCIDENT CLOSE TO THE FORMER RAPSODIE REACTOR AT THE CADARACHE SITE | CADARACHE, RAPSODIE, France |
| 21-12-1993 | INES 1 | TURBINE TRIP DUE TO PRESSURE DROP IN STEAM GENERATOR MAIN COLLECTOR | BOHUNICE-2, Slovakia |
| 16-03-1994 | INES 1 | REACTOR SCRAM CAUSED BY THE CABLE FIRE UNDER THE TURBINE HALL PREMISES | KHMELNITSKI-1, Ukraine |
| 03-03-1994 | INES 2 | COOLANT LEAK FROM THE AUXILIARY PRIMARY CIRCUIT CLEANUP SYSTEM DURING COOLDOWN OF THE PRIMARY CIRCUIT | KOLA-2, Russian Federation |
| 08-03-1994 | INES 0 | SHUNT TRANSFORMER INFLAMMATION AT THE HIGH-VOLTAGE (750 KW) LINE SWITCHYARD | ZAPOROZHE-1, Ukraine |
| 07-02-1994 | INES 1 | FAILURE OF THE FOAM FIRE-EXTINGUISHING SPRINKLER SYSTEM TO OPERATE FOR 16 HOURS DUE TO FROZEN PIPES | IGNALINA-1, Lithuania |
| 22-02-1994 | INES 0 | LEAKAGE OF FEEDWATER THROUGH WELDED JOINT OF A NB 76 PIPELINE CONNECTING ECCS HEADER WITH DISTRIBUTION GROUP HEADER | LENINGRAD-1, Russian Federation |
| 29-01-1994 | INES 2 | FAILING TO COMPLY WITH THE OPERATING PROCEDURES | BUGEY-5, France |
| 03-02-1994 | INES 0 | TURBINE TRIP AND REACTOR POWER DECREASE DUE TO FAILURE OF AUXILIARY TRANSFORMER AT NPP DUKOVANY | DUKOVANY-3, Czech Republic |
| 27-01-1994 | INES 0 | MANUAL REACTOR SHUTDOWN CAUSED BY THE FAILURE OF THE MANUAL REACTOR CONTROL ROD SYSTEM | IGNALINA-2, Lithuania |
| 18-01-1994 | INES 1 | CRACK IN CONTROL ROD HOUSING | JOSE CABRERA-1 (ZORITA), Spain |
| 24-12-1993 | INES 0 | FIRE IN ELECTRIC TRANSFORMER | ALMARAZ-1, Spain |
| 18-01-1994 | INES 0 | REACTOR SHUTDOWN CAUSED BY THE LEAKAGE DETECTED IN ONE OF THE REACTOR BUILDING ROOMS | IGNALINA-1, Lithuania |