1995-07-15INES 1ONE CLOSED VALVE IN THE CONTAINMENT PRESSURE RELIEF LINE TO THE ATMOSPHERE AND TWO CLOSED VALVES IN THE VENTING LINE TO THE EMERGENCY FILTERSwedenFORSMARK-2
1995-07-13INES 0SAFETY INJECTION DUE TO MAIN STEAM LINE LOW PRESSURESouth KoreaYONGGWANG-1
1995-07-10INES 1UNINTENTIONAL RELEASE TO THE SEA OF A MINOR AMOUNT OF SLIGHTLYCONTAMINATED WATERSwedenBARSEBECK-1
1995-07-09[N/A]SMALL SCALE FIRE IN THE SWITCHGEAR FOR THE SECONDARY CIRCUIT DURING SHUTDOWNCzech RepublicDUKOVANY-1
1995-06-20INES 0REACTOR SCRAM DURING INSPECTION OF GROUND CONNECTIONSlovakiaBOHUNICE-4
1995-06-20INES 0LEAK FROM LIFTING CHARGING PUMP RELIEF VALVEUnited States of AmericaH.B. ROBINSON-2
1995-06-02INES 1TURBINE/REACTOR TRIP CAUSED BY AN ERROR IN THE EH CONTROL SYSTEM OF THE TURBINE GENERATORSloveniaKRSKO
1995-05-28INES 1ROUTINE SURVEILLANCE REVEALS: STEAM GENERATOR SAFETY VALVES OPEN AT HIGHER PRESSURE THAN SPECIFIED AT THE RINGHALS 2. 3 AND 4 PWRSSwedenRINGHALS-2
1995-05-14INES 1SPURIOUS OPENING OF REACTOR COOLANT LIQUID RELIEF VALVECanadaBRUCE-5
1995-05-02INES 1SHORT VIOLATION OF LIMITS AND CONDITIONS DUE TO ONE AND A HALF HOUR UNAVAILABILITY OF 2 OUT OF 3 SAFETY SYSTEMSCzech RepublicDUKOVANY-1
1995-04-27INES 0REACTOR SCRAM DUE TO A REACTOR PROTECTION SPURIOUS SIGNALSlovakiaBOHUNICE-2
1995-04-27INES 0REACTOR TRIP DUE TO FEEDWATER CONTROL VALVE CLOSURESouth KoreaYONGGWANG-3
1995-04-09INES 0UNSUCCESSFUL SWITCH OVER FROM 400 KV TO 130 KVSwedenRINGHALS-2
1995-04-03INES 0REACTOR TRIP DUE TO MAIN FEEDWATER PUMPS STOPSouth KoreaKORI-3
1995-03-31INES 0CRACKS IN PUMP AND VALVE CASINGSSwedenOSKARSHAMN-1
1995-03-30INES 0UNIT SCRAM FOLLOWING THE LOSS OF OFF-SITE POWERSloveniaKRSKO
1995-03-25[N/A]GASEOUS RELEASE FROM NEARBY CHEMICAL PLANTUnited States of AmericaWATERFORD-3
1995-03-08INES 0REACTOR TRIP DUE TO ACTUATION OF GROUND FAULT RELAYSouth KoreaYONGGWANG-2
1995-02-25INES 0SAFETY INJECTION DUE TO PRESSURIZER SPRAY VALVE STACKSouth KoreaKORI-2
1995-02-23INES 0SMALL LEAKAGE OF PRIMARY COOLANT AT NPP BIBLIS, UNIT BGermanyBIBLIS-B
1995-02-14INES 1DROP TIME OF CONTROL RODS OUT OF CRITERIONChinaGUANGDONG-1
1995-02-13[N/A]CARBON DIOXIDE RELEASE TO A PLANT VITAL AREAUnited States of AmericaH.B. ROBINSON-2
1995-02-12INES 1NOT FULLY INSERTED CONTROL RODSSwedenRINGHALS-3
1995-02-07INES 0STEAM GENERATOR TUBE LEAK AT MAPS-2IndiaKALPAKKAM-2
1995-01-29INES 1HUMAN ERROR INITATED REACTOR TRIPUkraineCHERNOBYL-3