| date | INES  | title | location |
| 31-08-1994 | INES 1 | LEAKING ISOLATION VALVES IN THE EMERGENCY CORE COOLING SYSTEM | BARSEBECK-2, Sweden |
| 31-08-1994 | INES 1 | DAMAGE TO A SPENT FUEL ASSEMBLY DURING PREPARATORY OPERATIONS FOR REPROCESSING | MAYAK, RT-1, Russian Federation |
| 17-10-1994 | INES 1 | THROUGH WALL CRACK OF THE UPPER PART OF THE FUEL CHANEL TRACT NO. 41-13 | CHERNOBYL-3, Ukraine |
| 24-11-1994 | INES 1 | LOSS OF ELECTRICAL SUPPLY OF THE BANK PUMP STATION OF KOZLODUY NPP | KOZLODUY-1, Bulgaria |
| 26-08-1994 | INES 1 | MISSING LUBRICATION GREASE TO THE ECC SYSTEM'S CORE SPRAY PUMPS | BARSEBECK-1, Sweden |
| 28-09-1994 | INES 1 | PROTECTION SYSTEM FOR INITIATING BLOW DOWN NOT COMPLETELY REESTABLISHED AFTER REFUELLING OUTAGE | BARSEBECK-1, Sweden |
| 15-06-1994 | INES 1 | UNINTENTIONAL SLOW INSERTION OF ALL CONTROL RODS | FORSMARK-3, Sweden |
| 11-12-1994 | INES 1 | REACTOR AUTOMATIC SHUTDOWN BY SIGNAL OF NUCLEAR INSTRUMENTATION SYSTEMSYSTEM | ONAGAWA-1, Japan |
| 29-01-1995 | INES 1 | HUMAN ERROR INITATED REACTOR TRIP | CHERNOBYL-3, Ukraine |
| 12-02-1995 | INES 1 | NOT FULLY INSERTED CONTROL RODS | RINGHALS-3, Sweden |
| 12-08-1994 | INES 1 | INADVERTENT LOADING OF FUEL COLUMN DURING ON-POWER REFUELLING OF COOLANT CHANNEL | KALPAKKAM-1, India |
| 07-10-1994 | INES 1 | NON RETRACTION OF SOUTH FUELLING MACHINE GUIDE SLEEVE FROM CHANNELS S-12 | RAJASTHAN-2, India |
| 14-02-1995 | INES 1 | DROP TIME OF CONTROL RODS OUT OF CRITERION | GUANGDONG-1, China |
| 14-05-1995 | INES 1 | SPURIOUS OPENING OF REACTOR COOLANT LIQUID RELIEF VALVE | BRUCE-5, Canada |
| 28-05-1995 | INES 1 | ROUTINE SURVEILLANCE REVEALS: STEAM GENERATOR SAFETY VALVES OPEN AT HIGHER PRESSURE THAN SPECIFIED AT THE RINGHALS 2. 3 AND 4 PWRS | RINGHALS-2, Sweden |
| 02-06-1995 | INES 1 | TURBINE/REACTOR TRIP CAUSED BY AN ERROR IN THE EH CONTROL SYSTEM OF THE TURBINE GENERATOR | KRSKO, Slovenia |
| 03-01-1994 | INES 1 | RENDERING AN EMERGENCY FEEDWATER PUMP AND AN AUXILIARY EMERGENCY FEEDWATER PUMP AVAILABLE FOR A SHORT TIME WITHOUT ADHERANCE TO THE REQUIREMENTS OF THE TECSPECS | PAKS-4, Hungary |
| 14-07-1994 | INES 1 | SIMULTANEOUS INOPERABILITY OF TWO HIGH-PRESSURE ECCS PUMPS | PAKS-4, Hungary |
| 23-12-1992 | INES 1 | LEVEL DECREASE IN ECCS TANK 20TJ20B001,2 | PAKS-2, Hungary |
| 03-05-1993 | INES 1 | UNCONTROLLED INCREASE OF REACTOR POWER | PAKS-4, Hungary |
| 15-09-1993 | INES 1 | DETERIORATION OF NATURAL CIRCULATION | PAKS-2, Hungary |
| 08-05-1995 | INES 1 | INADVERTENT DISCHARGE OF LIQUID RADIOACTIVE WASTE | TARAPUR WASTE IMM. PLANT, India |
| 10-07-1995 | INES 1 | UNINTENTIONAL RELEASE TO THE SEA OF A MINOR AMOUNT OF SLIGHTLYCONTAMINATED WATER | BARSEBECK-1, Sweden |
| 02-05-1995 | INES 1 | SHORT VIOLATION OF LIMITS AND CONDITIONS DUE TO ONE AND A HALF HOUR UNAVAILABILITY OF 2 OUT OF 3 SAFETY SYSTEMS | DUKOVANY-1, Czech Republic |
| 07-06-1995 | INES 1 | PERSONNEL IRRADIATION IN A THERMAL POWER PLANT DURING MAINTENANCE WORKS | TPP BORZESTI, Romania |
| 24-11-1994 | INES 1 | LOSS OF OFF-SITE AC POWER | KOZLODUY-1, Bulgaria |
| 15-07-1995 | INES 1 | ONE CLOSED VALVE IN THE CONTAINMENT PRESSURE RELIEF LINE TO THE ATMOSPHERE AND TWO CLOSED VALVES IN THE VENTING LINE TO THE EMERGENCY FILTER | FORSMARK-2, Sweden |
| 22-11-1995 | INES 1 | AUTOMATIC REACTOR UNLOADING DUE TO SPURIOUS OPENINGS OF VALVES BETWEEN A GROUP OF ECCS PRESSURIZED TANKS AND REACTOR | IGNALINA-2, Lithuania |
| 30-11-1995 | INES 1 | OVEREXPOSURE OF OPERATOR DURING CALIBRATION OF IN-CORE SENSORS | IGNALINA-2, Lithuania |
| 31-10-1995 | INES 1 | HIGH RADIATION LEVELS IN REACTOR BUILDING | LASALLE-1, United States of America |